Monday, 19 December 2016

IBM 000-226 Questions

Question: 18

A customer with a POWERS 520 running IBM i 6.1.0 and internal disks plans to move to a Power 720 with external storage using NPIV. What is required to support this plan?

A. Upgrade to IBM i 7.1 TR6 or later
B. Install VIO Server with IBM i 7.1 TR6 client or later
C. Remain at IBM i 6.1 .0 and directly attach the V7000
D. Refresh to IBM i 6.1.1 and add the Native I/O Enablement feature

Answer: B

Friday, 19 August 2016

IBM 000-226 Questions

Question: 17

A customer has a large quantity of LTO-2 media.The customer would like to be able to read that media, while at the same time acquiring a tape library which supports hardware encryption.Which LTO format and attachment method supports these requirements?

A. SAS-attached LTO-5
B. USB-attached LTO-6
C. SCSI-attached LTO-3
D. Fibre-attached LTO-4

Answer: D

Thursday, 28 July 2016

IBM 000-226 Questions

QUESTION NO : 16

A customer wants to automate e-mailing the BRMS Recovery Reports to multiple e-mail addresses after the daily backup has run.Which of the following licensed program products is able to do this?

A.Portable Utilities for i (5733-301)
B.Transform Services for i (5770-TS1)
C.Advanced Job Scheduler for i (5770-JS1)
D.Advanced Function Printing Utilities (5770-API)

Answer: C 

Tuesday, 12 July 2016

IBM 000-226 Questions

QUESTION NO : 15

When virtualizing physical tape with IBM i Virtual Partition Manager (VPM) to client partitions, which statement is correct?

A.Only one client partition can use a virtualized device at a time.
B.IBM i client partitions can use supported tape libraries in Random mode.
C.Only tape drives located in the CEO are supported for virtualization to client partitions.
D.The hosting IBM i partition Network Storage Description (NWSD) default settings must be altered to allow use of virtualized tape.

Answer: A

Monday, 20 June 2016

IBM 000-226 Questions

QUESTION NO : 14

When could an IVM instance be preferable to an HMC for systems management?

A. Where multiple partition profiles are required
B. When Systems Director is used for centralized management
C. Where Power Compute Nodes are deployed in a PureFlex environment
D. When a single, entry-level Power Systems server needs to be split into client LPARs


Answer: D

Friday, 6 May 2016

IBM 000-226 Questions

QUESTION NO : 13

A customer with a POWERS 520 running IBM i is debating consolidating to a POWER7+770 that is currently only running AIX, or replacing the POWERS with a POWER7+720. The budget is limited, and the customer SWMA contract is expired. Which option is the most economical?

A. Transfer the IBM i license to the POWER7+770
B. Purchase a POWER7+ 720 and a new IBM i license
C. Purchase a new IBM i license for the POWER7+ 770
D. Purchase a POWER7+ 720 and transfer the IBM i license

Answer: B

Friday, 8 April 2016

IBM 000-226 Questions

QUESTION NO: 12

A customer with a POWERS 520 and a FC #0595 expansion unit wants to upgrade to a POWER7+720. The customer has TS2900 SCSI-attached tape drive and 20 70GB disk units.
Which elements of the original system can be used in the new system?

A. The TS2900 can be converted to SAS connectivity.
B. The memory DIMMS, if larger than 4GB, can be directly installed.
C. The EC #0595 expansion unit can be converted from HSL-2 to 12X.
D. The 70GB drive data can be migrated using Pack Utilities Maintenance Program in SST.

Correct Answer: A

Friday, 1 April 2016

IBM 000-226 Questions

QUESTION NO: 11

A customer with a POWERS 520 running IBM i 6.1.0 and internal disks plans to move to a Power 720 with external storage using NPIV. What is required to support this plan?

A. Upgrade to IBM i 7.1 TR6 or later
B. Install VIO Server with IBM i 7.1 TR6 client or later
C. Remain at IBM i 6.1 .0 and directly attach the V7000
D. Refresh to IBM i 6.1.1 and add the Native I/O Enablement feature

Correct Answer: B