QUESTION NO: 1
A P0WER6 customer with IBM i is migrating to a new POWER7 server and wants to transfer their existing IBM i processor entitlements.What is required for the donor and receiving machines to qualify for the transfer?
A. Both must have either IBM i 5.4, i 6.1, or i 7.1
B. Both must have the Enterprise Enablement feature
C. Both must have the same number of core activations
D. Both must be entitled at the same version and release of IBM i
Answer: D
QUESTION NO: 2
A customer is migrating from POWERS 520 to a POWER7¡Â 720.The migration includes the transfer of IBM i Licensed Program Products, and both systems need to run in parallel production for 30 days.Which action supports this requirement?
A. Request temporary migration keys
B. On/Off Capacity on Demand Licensing
C. Use temporary CBU keys during the migration period
D. Include IBM Temporary Software License for i product in the configuration
Answer: D
QUESTION NO: 3
Which of the following is one of the benefits provided by the integrated storage management capability of IBM ?
A. Eliminates the need to reorganize DB2 objects
B. Removes the requirement for redundant disk cache
C. Provides disk protection such as RAID-5, RAID-6, Hot-Spare or Mirroring
D. Allows for quick adaptation of new storage innovations such as Solid State Drives
Answer: D
QUESTION NO: 4
A customer has a production 16-core POWER7+ 770 with 8 cores currently active.They are considering purchasing a POWER7¡Â 770 Capacity Back Up (CBU) with the same processing capacity.What must be included in the new POWER7+ 770 CBU configuration?
A. The CBU feature, (8) core activations and (8) processor entitlements of IBM i
B. The CBU feature, no core activations and a minimum of (1) processor entitlement of IBM i
C. The CBU feature, (8) core activations and a minimum of (1) processor entitlements of IBM i
D. The CBU feature, no core activations, (1) processor entitlements of IBM i and (1) Enterprise Enablement feature
Answer: C
QUESTION NO: 5
A customer with a POWERS 520 and a FC #0595 expansion unit wants to upgrade to a POWER7+720. The customer has TS2900 SCSI-attached tape drive and 20 70GB disk units.Which elements of the original system can be used in the new system?
A. The TS2900 can be converted to SAS connectivity.
B. The memory DIMMS, if larger than 4GB, can be directly installed.
C. The EC #0595 expansion unit can be converted from HSL-2 to 12X.
D. The 70GB drive data can be migrated using Pack Utilities Maintenance Program in SST.
Answer: A
QUESTION NO: 6
A customer needs to permanent, archive multiple terabytes of data on a daily basis.The data annot be overwritten and needs more than a software-based enforcement method.Which product supports this need most economically?
A. DVD-ROM
B. Secure USB
C. Optical platters
D. LTO WORM media
Answer: B
QUESTION NO: 7
Which of the following is a restriction when virtualizing tape or DVD with VIO Server to client partitions?
A. All client partitions have shared access to the virtualized device.
B. Only one client partition can use the virtualized device at a time.
C. Only AIX and Linux client partitions have shared access to the virtualized device.
D. All IBM i client partitions have shared access to the virtualized device.
Answer: B
QUESTION NO: 8
An IBM i 7.1 customer with a Power 720 needs to occasionally run a small test environment of IBM i. The environment doesn’t require regular backups, availability isn’t a factor, and consistent I/O performance isn’t important.The test environment needs to be deployed quickly, and must be redeployed with a fresh instance
after testing.Which of these following configurations supports these requirements?
A. IBM i as a client partition of IBM i
B. Dedicated internal storage and network
C. Storage and network managed with VIO Server
D. Storage managed with VIO Server, dedicated network
Answer: A
QUESTION NO: 9
A Power 770 customer is considering the purchase of a Power 770 Capacity Back Up (CBU) system as part of a disaster recovery solution. What is a benefit provided by CBU?
A. Allows the temporary transfer of active cores from the primary system to the CBU.
B. Allows the temporary transfer of license keys from the primary system to the CBU.
C. Allows the temporary transfer of IBM i licenses and user entitlements from the primary system to the CBU.
D. Allows the temporary transfer of IBM i licenses and Enterprise Enablement features from the primary system to the CBU
Answer: D
QUESTION NO: 10
A customer running IBM i VSR4MO on a POWERS 520 is considering purchasing a POWER7+720.What steps should be performed as part of the upgrade/migration process?
A. Upgrade to V5R4M5 Run STROBJC VN to prepare programs for 7.1.
B. Upgrade the current machine to 6.1Run ANZOBJCVN Then upgrade to 7.1 to support the new hardware
C. Run ANZOBJCVN on their current V5R4M0 system to identity potential program issues.
D. Upgrade to 6.1 Run ANZOBJCVN to determine if the customer can upgrade to IBM i 7.1
Answer: C